Consequently, the" E2A" Panel has found that such losses are the direct result of Iraq' s invasion and occupation of Kuwait.
因此,小组认定,索赔人遭受损失或伤害的地点本身并不能确定委员会的权限。
Accordingly, the Panel has found that the place where the loss or damage was suffered by the claimant is not in itself determinative of the Commission' s competence.
小组认定,在不了解清单所列各项价值的情况下,无法将其作为可赔损失加以核实和估价。
The Panel has decided that, without knowing the value of the individual items on the list, it is impossible to verify and value these items as compensable losses.
The Panel finds that such expenditure is compensable in principle pursuant to Governing Council decision 7(S/AC.26/1991/7/Rev.1).
但是,“C”小组认定这件索赔包括一个注册实体的损失。
However, the category“C” Panel had identified this claim as including the losses of an incorporated entity.
根据迄今取得的进展,总部公共部门会计准则小组认定,法庭正在按部就班地实施公共部门会计准则。
On the basis of the progress achieved thus far, the Headquarters IPSAS team has determined that the Tribunal is on track in terms of IPSAS implementation.
小组认定,合理的折旧率是将设备在整个项目周期内完全折旧。
The Panel has determined that the appropriate depreciation rate is one that would result in the complete depreciation of the equipment over the life of the Project.
Given that Polytechna received compensation for its alleged financial losses, the Panel finds that Polytechna failed to demonstrate that it has suffered a financial loss.
With respect to the" payment of war claims" and the amounts outstanding under the deferred payment arrangement, the Panel finds that all work under the contract was completed prior to 2 May 1990.
In fact, based on evidence obtained following the filing of the claim, the Panel determined that the PNZ production rate was 133,436 BPD, which gives SAT a share of 66,718 BPD.
Moreover, as the expenses began to run from July 1990, the Panel finds that the alleged expenses were not incurred as a direct result of Iraq' s invasion and occupation of Kuwait.
The Panel finds that Iraq' s invasion and occupation of Kuwait was the direct cause of the project collapsing and the consequent failure of TJV to recover its bid costs."(Paragraph 519.).
The Panel found that the safeguard measures fell outside the scope of Article 5.7 of the SPS Agreement, which allows members to adopt provisional SPS measures where relevant scientific evidence is insufficient.
The Panel finds that for the purposes of the" arising prior to" clause in paragraph 16 of Security Council resolution 687(1991), National Engineering had, in each case, a contract with Iraq.
The Panel found that, based on the claimant' s evidence as to when final commissioning would generally occur, 12 months was a reasonable period for the purposes of this claim.
依据索赔人提交的证据,小组认定,这名非科威特籍索赔人在伊拉克入侵和占领科威特之日是企业的独资业主。
On the basis of the evidence submitted by the claimants, the Panel finds that the non-Kuwaiti claimant was the sole owner of the business at the date of Iraq' s invasion and occupation of Kuwait.
In addition, the Panel found that further adjustments were required to offset the risk of overstatement relating to the possibility that certain of these amounts were in fact uncollectible receivables.
Under the circumstances, the Panel finds that Iraq' s invasion and occupation of Kuwait(and the consequent national freezing order) was not the direct cause of the claimant' s loss.
小组认定,所有223个索赔人都是在可赔期内离开伊拉克,因此原则上有资格就与离开有关的损失得到赔偿。
The panel found that all 223 claimants had departed from Iraq during the operative period and were therefore, in principle, eligible to receive compensation for their departure losses.
In addition, the Panel finds that the period from 3 March 1991 to 2 August 1991 is a reasonable secondary compensation period, at the end of which this type of business could be expected to resume normal operations.
English
Bahasa indonesia
日本語
عربى
Български
বাংলা
Český
Dansk
Deutsch
Ελληνικά
Español
Suomi
Français
עִברִית
हिंदी
Hrvatski
Magyar
Italiano
Қазақ
한국어
മലയാളം
मराठी
Bahasa malay
Nederlands
Norsk
Polski
Português
Română
Русский
Slovenský
Slovenski
Српски
Svenska
தமிழ்
తెలుగు
ไทย
Tagalog
Turkce
Українська
اردو
Tiếng việt