Advance payment: 10% of net contract value.
bank guarantee for 5% of the net contract value and part two, deposit amounting to 5% of the net value of each invoice.
The total liability of the Contractor to the Ordering Party is limited to 20% of net contract value.
the completion date or the date of completion of any stage cannot exceed 12% of the net contract price.
The total limit of all contractual penalty fees on the side of the Contractor for boiler K2 under any title is 22% of the net Contract value for this boiler.
A delay pertaining to the general execution deadlines: 1% of the Net Contract Value for each full week.
whose totalamount for all titles shall not exceed 20% of the net contract price.
In connection with the extension of range of the Contractor's work on the boiler K2 the net Contract value is also higher by 39,9 m PLN.
of liquidated damages for delay and unachieved Performance Guarantees shall not exceed 35% of the net contract value.
the Contractor- 10% of the net contract value.
0.15% of the net Contract Value for each day of the delay.
The Contractor shall pay the Company a contractual penalty at the amount of 10% of the net Contract value for either party withdrawing from the Contract through the Contractor's fault.
The total net Contract value for boiler K-1
Liquidated damages of 10% of the net contract value in the event of the withdrawal from the performance of the contract due to circumstances for which the Contractor is responsible;
the Contractor shall pay the Investor liquidated damages of 0.1% of the net contract price for each day of delay in defect rectification.
shall not exceed 60% of the net contract price.
the project manager entering the building, the Contractor shall be obliged to pay the Investor liquidated damages of 25% of the net contract price.
The Company is entitled to charge a contractual penalty at the amount of 0.05% of the net Contract value for every commenced day of delay for exceeding the deadline for the elimination of faults/ defects/ shortcomings during the guarantee period.Â.
The Contracting Party shall pay the Contractor liquidated damages of 0.02% of the net contract value for every day of delay in handing over the construction site
shall not exceed 45% of the net contract price.