Примеры использования Project schedule на Английском языке и их переводы на Русский язык
{-}
-
Official
-
Colloquial
At the last seminar was revised project schedule for the coming year.
XML Schemas are complete for Project Schedule.
Implementation plan including a Gantt Chart or Project Schedule indicating the detailed sequence of activities that will be undertaken
A summary project schedule for the new facility is contained in annex III to the report of the Secretary-General.
Project schedule for construction of additional office facilities at the United Nations Office at Nairobi.
Ensure exact delivery time to make sure your project schedule will not be affected even by one day.
such as project schedule, agencies may inadvertently cause various problems.
presented in the sixth progress report, a tentative new project schedule was introduced.
the structure of volumes, the possible co-authored publications' topics and the project schedule for next year.
He commended the Ethiopian Government on its support for the construction of additional office facilities at ECA and hoped that the project schedule would be respected.
The reports stated that the design documents were not advanced enough for a well-informed opinion to be made by the Board on the project schedule and cost estimates.
while at the same time stressing the need for decisive action to restore the project schedule.
the Secretariat could take quick decisions concerning contract amendments to avoid delays in the project schedule.
Whatever the solution, it must be agreed before it impacts on the project schedule to avoid further cost increases.
3 of the strategic capital review outlined in the project schedule included in the present report;
The Chief Executive Officer had provided assurances that the System would be delivered according to the project schedule and on or possibly below budget.
would guide them to take appropriate action to complete the project schedule.
conmstruction work was carried out at the SHPP Jonouli 1 according to the project schedule.
A major challenge was the extremely tight project schedule, as the new plant was to supply purified water to the internal net by the be- ginning of september 2007.
The result is an overall reduction in the project schedule from five years and three months to four years.